President Ferdinand Marcos Jr. claimed in his third State of the Nation Address (SONA) that the country’s infrastructure development remains “on schedule.”
This needs context. Some projects under the “Build Better More” program have been delayed and completion dates were adjusted due to issues involving right-of-way (ROW) acquisition, land turnover and lack of funding.
STATEMENT
Marcos said:
“As we enter the midterm, our infrastructure development remains sustained, strategic, and on schedule.”
Source: RTVMalacanang, State of the Nation Address (SONA) 2024, July 22, 2024, watch from 15:29 to 15:36
The president added that the country is in the middle of a “railway renaissance,” ensuring that ROW issues would be resolved to “not get in the way” of infrastructure development.
FACT
The completion dates of at least six of the 185 Infrastructure Flagship Projects (IFPs), including the Samal Island-Davao City (SIDC) Connector Bridge, the Metro Manila Subway Project and the Metro Rail Transit Line-7 (MRT-7), have been adjusted due to delays.
Project | Start Date | Original Date of Completion | New & Revised Date of Completion |
---|---|---|---|
Metro Manila Subway Project | 2018 | 2027 | 2029 (full operations) |
Samal Island-Davao City Connector Project | October 2022 | 2027 | September 2028 |
MRT-7 | April 20, 2016 | 2019 | Q4 2025 |
North South Commuter Railway (Malolos-Tutuban) | July 2, 2019 | Q4 2021 | Q4 2026, Q3 2029 |
North-South Commuter Railway – PNR North 2 (Malolos-Clark) | Sept. 18, 2021 | Q2 2023 | Q4 2024, Q4 2026 |
North-South Commuter Railway – PNR South (Manila-Calamba) | July 3, 2023 | April 2028 | Q1 2028, Q2 2029 |
In a June 6 press release, Marcos acknowledged the need to amend the ROW process, noting that it has caused a “huge delay” in some IFPs.
ROW is a designated part of a property set aside for use in a national government project, as defined by Republic Act No. 10752.
VERA Files reported in May that the four-kilometer SIDC Connector Project has not seen any progress since its groundbreaking in October 2022 because of unresolved ROW acquisition issues.
The MRT-7 line has faced multiple delays where the completion of the Bulacan stations was pushed to 2027 due to ROW issues. Its construction began in April 2016 and was initially set to be operational by 2020.
Meanwhile, land acquisition and delayed payments hound the 33-kilometer Metro Manila Subway Project, which was originally set to be operational in July 2027. The Department of Transportation (DOTr) said the P488.48-billion project is 15% complete as of July 19.
Marcos has asked the DOTr to look for alternative funding sources for the Tagum-Davao-Digos railway, which has been stalled after the government refused to obtain Chinese loans for its financing.
BACKSTORY
Of the 185 IFPs, three projects have been completed, eight are under construction and six have been approved as of July 2024. The indicative total value of these projects is at P9.14 trillion.
(The author is a journalism student at the UP College of Mass Communication and is doing her internship with VERA Files.)
Check out these sources
National Economic and Development Authority, Neda Board Approves Updated Ifp List, Other Projects To Support Infra Dev’t, Feb. 27, 2024
Presidential Communications Office, PBBM backs ‘old system’ to address ROW issues to speed up key infra projects, June 6, 2024
GMA Integrated News, Marcos supports old process of addressing right-of-way issues, June 6, 2024
Department of Public Works and Highways, Implementing Rules and Regulation of Republic Act No. 10752, May 25, 2016
House of Representatives, Meeting of the Committee on Transportation, Feb. 16, 2023
PhilStar.com, MRT-7 construction suffers another delay, May 20, 2024
IBON, 19 years and counting: The story of MRT-7, May 7, 2023
Philippine Information Agency Davao Region, Kapehan sa Dabaw, June 10, 2024
Inquirer.net, Right-of-way problems threaten to delay MRT 7 project, Aug. 8, 2018
Inquirer.net, MRT-7 will be operational before the end of next year, says DOTr, June 4, 2024
BusinessWorld, Completion of SMC’s MRT-7 delayed on RoW issues in Bulacan segment — DoTr, May 20, 2024
Inquirer.net, Right-of-way problems threaten to delay MRT 7 project, Aug, 8, 2018
Inquirer.net, DOTr: Only 55% of right-of-way acquired for Metro Manila Subway, March 8, 2024
Rappler, FAST FACTS: What’s the Metro Manila Subway?, March 7, 2024
PhilStar.com, Right of way, budget woes delay buildup of rail projects, May 22, 2024
ABS CBN News, DOTr: Metro Manila Subway Project about 15% complete, July 19, 2024
RTVMalacanang, 125th Founding Anniv of DOTr and Ceremonial Signing of the Civil Works Contracts for DPTMP, July 2, 2024
GMA Integrated News, Marcos tasks DOTr, DOF to explore fund sources for Tagum-Davao-Digos railway, Feb. 7, 2024
PhilStar.com, President Marcos: Look for new fund source for Mindanao railway, Feb. 8, 2024